ACCEPTANCE TESTING
The term “Acceptance Testing” refers to the process of performing initial tests on new electrical equipment once it’s received from the manufacturer. Acceptance testing serves many purposes:
- to verify that the new equipment meets the performance specifications as measured by the manufacturer
- verifies the integrity of the installation and conformance to applicable industry standards
- serves as a benchmark for which all future testing should be compared to
To fully maximize the benefits acceptance testing can provide, it should only commence after the new equipment is placed and fully installed. Furthermore, it should be performed by an independent 3rd party when possible, working with the end user’s interest in mind. Well-executed acceptance testing is a must for long-lasting, reliable service.
COMMISSIONING
Often confused with Acceptance Testing, “commissioning” refers to the process of preparing for and energizing electrical equipment for the first time. In this stage, equipment transitions from being considered a new installation to being “in service”. Performed sequentially after Acceptance Testing, commissioning tests are necessary to verify the proper functionality of the system controls and protection schemes. While often overlooked, commissioning tests are vital to ensuring safe and reliable equipment operation. Improper commissioning can result in significant, possibly catastrophic, equipment and facility damage.
MAINTENANCE TESTING
Once in service, the need to perform electrical testing doesn’t end. To ensure continued safe and reliable operation, maintenance testing should be considered. “Maintenance Testing” refers to the periodic testing and evaluation of in-service electrical equipment. Maintenance testing, when performed at regular intervals, can provide the following benefits:
- Increased reliability and uptime; production
- Preemptive identification of equipment failures, allowing them to be addressed in a more controlled manner.
- Identifies unauthorized modifications and alterations to system configuration and provides an opportunity to correct them.
Periodic Maintenance Testing can help ensure your equipment works reliably for years to come.